England remediation plan targets faster higher-risk building safety works

Remediation plan targets faster decisions

The Building Safety Regulator (BSR) has introduced an external remediation improvement plan to reduce delays to higher-risk building safety works across England.

BSR said the plan includes a dedicated external remediation multidisciplinary team, lower average caseloads for regulatory leads and wider use of approval with requirements where appropriate.

The regulator said it will recruit more staff to reduce individual caseloads from an average of 25 to around 10.

The new multidisciplinary team will be supported by external remediation account managers handling applicant communications and portfolio concerns.

BSR also plans to pilot the use of building control professionals from different classes to support case officers and regulatory leads.

A new consistency process will be introduced to resolve technical disputes more quickly.

The regulator is also moving towards more direct engagement with applicants, including initial meetings for more complex projects.

BSR said it will publish a clear external remediation prioritisation structure and is working on digital visibility changes so applicants can track progress after submission.

Older cases and application quality

BSR said around 40% of ongoing external remediation applications rely on government funding, and many older complex cases are taking longer to reach decisions.

The regulator said internal resource constraints and a high volume of older non-compliant industry submissions are driving the current caseload.

Incomplete applications are delaying decisions where required technical information or legal documentation is missing.

Examples include limited evidence of fire-resistant properties for replacement cladding and related materials, missing structural loading calculations and incomplete demonstration of thermal performance.

Delays are also linked to incomplete design information, unsupported non-worsening claims and poorly organised documents.

Ambiguity over retained combustibles is also described as a frequent cause of failure.

BSR said it has published initial guidance for external remediation work on existing higher-risk buildings and will issue more feedback, resources and support in the coming months.

The regulator is also planning better data sharing with organisations managing government funds, including Homes England.

By December 2026, BSR is aiming to reduce average decision times for remediation applications to less than 12 weeks and achieve approval rates above 65%.

Lord Roe, BSR Board Chair, said: “We continue to accelerate our decision-making for new build applications, speeding up approvals for new build and external remediation projects and increasing the supply of safe new and existing homes through the recent changes we have made to our processes.

“We recognise current determination times for remediation cases are falling short of statutory targets.

“This plan represents a targeted and achievable package of measures to reset the system and clear older legacy remediation cases.

“By doing so and then focussing on more recent applications, we can ensure high-rise residents see essential safety improvements they deserve without unnecessary or further delays.”

Charlie Pugsley, Acting CEO of BSR, added: “As we enter an important new chapter as a standalone regulator, our focus is on strengthening safety, rebuilding trust and supportively collaborating with industry.

“Collectively these measures will ensure current and future remediation applications can proceed as smoothly and quickly as possible.

“By launching a dedicated multidisciplinary team and introducing account managers, we are dramatically increasing our capacity to make faster decisions.

“Speed cannot come at the cost of safety.

“We will also publish further specific guidance and support to help industry submit higher-quality applications, ensuring thousands of residents can feel safe, and are safe in their high-rise homes.”

Building Safety Regulator becomes standalone body in Gateway 2 reform milestone

Gateway 2 framework and transition to standalone status

The Building Safety Regulator officially became a standalone organisation on 27 January 2026, marking a structural shift in the delivery of Gateway 2 building control oversight.

The Building Safety Regulator (BSR), previously part of the Health and Safety Executive (HSE), transitioned to an arm’s-length public body under the Ministry of Housing, Communities and Local Government, paving the way for the creation of a single construction regulator as recommended by the Grenfell Tower Inquiry.

The regulator was established in 2021 following the Grenfell Tower tragedy, with full statutory powers introduced under the Building Safety Act 2022.

The move formalises a broader mandate that extends beyond high-rise buildings to include responsibility for safety standards across all buildings in England.

The transition follows what BSR described as an operational reset in its role as the building control authority for higher-risk buildings, supported by the introduction of its Innovation Unit and new efficiency measures.

These changes were positioned as part of efforts to improve operational delivery, target regulatory guidance and support competence development across the construction sector.

Regulatory mission, leadership and sector response

Lord Roe, Chair of BSR, said: “Today is a decisive and important step in strengthening building safety and a milestone that marks our evolution into a standalone regulator.

“While the creation of BSR in 2021 was a watershed moment, today is about looking forward to a single construction regulator that brings coherence to a once-fragmented system.

“We will know we are successful when residents acknowledge we have made the built environment safer.

“Today is about continuing to support homes being built safely while fulfilling our primary mission: ensuring we are all building better and living safer, together.”

Charlie Pugsley, Acting Chief Executive Officer of BSR, said: “Today is a significant new chapter for BSR, with a clear signal that while we must continue to focus on improving our operational delivery for both new build homes and occupied HRBs, our mandate extends far beyond high-rise oversight to a broader responsibility for safety and standards across buildings in England.

“By driving professional competence and refining regulatory guidance, we can ensure a holistic approach that spans from initial design through to lifelong building management.

“Our commitment to robust enforcement and cultural transformation serves a single, vital purpose in 2026 and beyond – restoring resident confidence and trust in the built environment.”

Samantha Dixon, Building Safety Minister, said: “Everyone deserves to live in a safe home and we are determined to deliver lasting change to make this a reality.

“The Building Safety Regulator sits at the heart of this mission, and today launching a new body is an important step in realising sector wide reform.

“I look forward to working with the new leadership team on our journey towards the Single Construction Regulator.”

Mark Reynolds, Executive Chair of Mace Group and Chair of the Construction Leadership Council, said: “Over the last twelve months we’ve seen a very tangible shift in how BSR has worked with the Construction Leadership Council and developers across the country, and the result has been a more effective process, enabling safer buildings to be commissioned and delivered faster.

“The UK needs confidence that the construction industry, the regulator and government are all working together to deliver new and safe housing at scale – and I believe this moment marks a major step forward on that journey.

“As an independent body and working under the leadership of Charlie and Andy I have no doubt we’ll see more positive progress during 2026.”

The transition formalises BSR’s independence and establishes its governance framework as the regulator works toward the development of a single construction regulator model.

Regulatory role and standalone status

The Health and Safety Executive (HSE) outlined the regulatory framework and operational changes following the transition to standalone status.

The HSE described the Building Safety Regulator as the national regulator responsible for improving the safety and standards of all buildings in England, established in 2021 following the Grenfell Tower tragedy, with full statutory powers introduced under the Building Safety Act 2022.

From 27 January 2026, BSR operates as a stand-alone executive non-departmental public body sponsored by MHCLG, with governance and accountability formalised while day-to-day regulatory activity continues.

The framework includes responsibility for regulating higher-risk residential buildings over 18 metres or seven storeys across design, construction and occupation through a three-stage gateway approval process.

BSR also acts as the building control authority for all higher-risk buildings, including hospitals and care homes, and oversees the performance of local authority and private sector building control bodies.

Charlie Pugsley, Acting Chief Executive Officer of the Building Safety Regulator, said: “This month marks a significant new chapter for BSR as a standalone body, with the knowledge that our new processes are driving improvements – evidenced by the fact we recently made the most decisions in our operating history.

“We are determined to build on this momentum by launching a Remediation Improvement Plan to tackle complex remediation cases and streamline resources.

“We will also be engaging even more closely with applicants to help improve the quality of new build HRB applications.

“By driving these improvements, we can ensure we keep essential construction projects being built, while upholding the critical safety standards that protect residents in both new and existing homes.”

Gateway 2 decisions and application volumes

The Building Safety Regulator published new building control approval data covering November 2025 to January 2026.

The Building Safety Regulator (BSR) recorded 698 Gateway 2 decisions across all application types in the 12 weeks to 24 January 2026.

Live applications across all categories totalled 1,159.

The final quarter of 2025 recorded 673 decisions by 31 December, compared with just over 200 in early 2025.

Across all Gateway 2 categories, 68% of decisions related to London cases, totalling 476 decisions in the capital since November.

In the 12 weeks to 24 January, 97 Gateway 2 new build applications received decisions and 99 new build applications were submitted.

New build applications represented 19,600 residential units.

Decisions were issued for 19,914 units, including 11,962 approvals.

Live cases represented 37,065 residential units.

Legacy, remediation and Innovation Unit performance

The update set out volumes and decision outcomes for legacy applications, remediation cases and the BSR Innovation Unit alongside new build activity.

Since November, 52 decisions were made on outstanding legacy cases inherited under the previous model, with 29 in London.

The approval rate for historic applications viable to receive a decision reached 87%.

The remaining 29 complex legacy cases were under assessment to determine whether continued resources were warranted or whether rejection and resubmission would be required.

Since 3 November 2025, 75 remediation decisions were issued and 73 new remediation cases were received.

Live remediation cases totalled 286, representing 24,949 units.

A batching pilot delivered 12 decisions, with a Remediation Improvement Plan scheduled to launch in the coming weeks to address application quality and streamline internal resources.

In the past 12 weeks, the BSR Innovation Unit (IU) recorded 39 decisions, with 27 in London.

The IU managed 111 live new build applications representing 25,226 units, including 61 in the capital.

Of cases progressing beyond validation, 30% were approved and 41% were rejected.

Initial validation failure rates reached 56%, linked to missing basic design information.

Industry reaction on Gateway 2 evidence and digital records

Rob Norton, UK Director at PlanRadar, said: “The BSR becoming a standalone body corporate is the final nail in the coffin for ‘analogue’ site management.

“For years, the industry has treated documentation as a post-script, something to be tidied up at the end of a project.

“Those days are over.

“An independent regulator, equipped with its own board and a dedicated enforcement mandate, isn’t going to accept a ring-binder full of blurred photos and missing signatures as proof of safety.

“The real challenge for Gateway 2 and 3 isn’t the regulations themselves, it’s the evidence.

“We are currently seeing a massive disconnect between on-site reality and regulatory reporting, which is the single biggest factor behind the Gateway delays currently stalling UK construction.

“If the BSR is to succeed in clearing these backlogs as an independent entity, it requires high-quality, tamper-proof digital data.

“Without a robust ‘Golden Thread,’ developers are essentially playing Russian Roulette with their completion certificates.

“This independence should be a wake-up call.

“The BSR now has the autonomy to set a higher bar for digital competence.

“We can’t expect to build the next generation of high-rise homes using the record-keeping standards of the 1990s.

“It’s time for the industry to stop viewing digital tools as an ‘extra’ and start seeing them as the only way to stay on the right side of an empowered regulator.”

Dr David Crosthwaite, chief economist at BCIS, said: “Data published by the Building Safety Regulator (BSR) in the past few months has spoken for itself.

“While more building control approval decisions are being made thanks to the new Innovation Unit, the speed of decision-making, specifically for remediation applications, must improve.

“Establishing the BSR as an independent organisation is certainly an important step toward unifying and simplifying how construction is regulated.

“It shows the industry is being listened to in the same way the BSR’s process adaptations did last year.

“That said, the BSR cannot afford to take its foot off the gas.

“Its new caseload is growing and construction’s residential market particularly would benefit from a slicker regulatory system sooner rather than later.

“Both private and public sector housing output has slowed and fewer approval holdups would go a long way to speed up project starts and the economic value they can deliver.”

AEI Cables calls for Building Safety Act to be widely understood

AEI Cables has said the performance of cabling in critical fire safety systems needs to be clearly understood as part of the new Building Safety Act.

The new Building Safety Act makes requirements for higher-risk buildings which are those deemed to be of at least 18 metres in height or at least seven storeys containing at least two residential units.

The Act updates guidelines for construction and management of higher risk buildings and covers the whole supply chain including electrical safety systems and cabling. The current British Standard Code of Practice BS 8519 identifies six categories of power and control cables with survival times of 30, 60 or 120 minutes. 

General Manager, AEI Cables, Stuart Dover’s statement

Stuart Dover, General Manager of AEI Cables, said: “There is a lot of new detail in the legislation and we welcome the requirements of the Act. However, there is a pressing need to understand the part played by electrical safety systems and the cabling that operates these systems.

“There is good information available through the cabling industry including our own technical advisers about cable testing, cable classifications and cable performance in real fire conditions.”

The systems in these buildings powered by electrical cables, including smoke and heat extraction systems, assist fire services in firefighting and a safe evacuation in the case of life safety.

The Building Safety Regulator

The Building Safety Regulator will oversee the safety and performance of all buildings, as well as having a special focus on high-rise buildings. It will promote competence and organisational capability within the sector including for building control professionals and tradespeople.

Building owners should now have their building safety regime in place and any occupied higher-risk buildings should be registered with the Building Safety Regulator.

New legislation needs to be welcomed, says AEI Cables: Summary

AEI Cables has called for the updates to the Building Safety Act to be widely understood. AEI’S General Manager said that there is a pressing need to understand the part played by electrical safety systems and the cabling that operates these systems.