Gateway 2 lessons: Preparing construction projects for Gateway 3 success

Quelfire shares expert insights into the key lessons from Gateway 2, highlighting common compliance challenges and how construction teams can prepare for Gateway 3

In many ways, Gateway 2 has become the new normal. It’s already changing the industry for the better, especially for teams that genuinely want to get things right. That said, the industry isn’t fully there yet.

Some still hold the mindset of “we’ve always done it this way” and approach the Gateway regime as something they have to do, rather than as something that can make a real difference in how we design and construct buildings.

From our perspective at Quelfire, it’s a much-needed change that is pushing the industry toward better decisions and safer buildings – which can only be good things, surely? In early applications, Ishfaq was surprised by the disconnect between the Building Safety Regulator (BSR) teams and the construction industry.

He highlighted that there seemed to be no established process; some BSR teams used staged applications, while others required full submissions.

Some submissions completed in early Stages 3/4 with no contractor details were approved in 12 weeks, whereas other T1 contractors, for instance, provided thorough information on specific parts of the build and waited about 9 months for approval.

Ultimately, this suggests that the BSR was still very much working out its processes during this stage. Because the introduction of the Gateways was such a significant change for the industry, the focus has naturally been on the first stop-and-go gateway, Gateway 2.

However, as the built environment transitions beyond this, the next unknown is Gateway 3, which introduces a new level of uncertainty. Ishfaq raised concerns about potential delays from Gateway 3, especially given the delays experienced with the second Gateway.

He believes it hasn’t been “road tested enough yet” to know what it will entail; the industry is still waiting for feedback.

Where are construction projects still falling short at Gateway 2?

Typically, R5 Consultants will distribute their project schedule to key parties, ready for submission at Gateway 2.

However, upon receiving the completed schedule, the team often finds gaps in expectations and information, with each party often having different ideas about elements of the project.

Ishfaq said, “The challenge with firestopping is that it’s one of the few elements of construction that is genuinely collaborative. The architect will set their position of all these walls, the structural engineer will dictate what size the openings and letterboxes can be and then the M&E engineer needs to tell you what is actually passing through and where and then you can come to a resolution on what the firestopping needs to be.” What Ishfaq and his team are finding is that they’re getting pushback from consultants due to tight deadlines and rising costs, because they haven’t given enough time to Gateway requirements.

Furthermore, Whitty argued that contractors “can’t play the system anymore” and that part of the Gateway regime is about making concrete decisions and following them through on-site.

He said that hidden costs, along with having to redesign a project two or three times, slow development and cost a lot of money to resolve.

What does good Gateway 2 compliance actually look like?

The whole reason for the Building Safety Act 2022 and subsequent Gateways is to improve building safety and protect those in them. Early fire stopping engagement is the only way to ensure this, as it brings all key parties together at the design stage to discuss key deliverables and how they’ll be achieved.

It puts fire safety at the heart of every decision, ensuring the project is designed and then built around available fire stopping tested solutions. Ishfaq said that when looking at the mechanics of what you’re going to submit, it is about design procurement alongside product and system procurement.

If contractors review the information and decide on deliverables, a systematic approach can be taken to articulate it to the regulator.

Further to this, Whitty stated that main contractors need to be clear about and commit to products and systems they want to see in the building. He also raised that you’ve got to make it easy for the regulator to say yes.

You’re taking the BSR on a journey – give examples, show the rationale behind the decisions. This also includes being in dialogue with your regulator spokesperson and finding out what’s required of you: ask the questions.

All panellists agreed that it is better for project teams to take their time at the design stage and focus on getting it right the first time. Multiple redesigns cost time and money, add project pressure and stress and ultimately slow the whole project down.

You might discover that the BSR will ask for additional information after submission. By putting in the effort beforehand, you give yourself an advantage.

Thorough design may take time upfront, but it pays off in the long run for business security and profitability. Not to mention it prioritises building safety!

How can construction teams start preparing for Gateway 3 now?

Both Whitty and Ishfaq agreed that contractors need to improve their QA process. Whitty also went on to say that it’s about the execution of what you set out to do. It’s about evidencing that what you have installed is as per what you submitted at Gateway 2.

You can’t leave it to the last minute to prove how your piling went in, for example, you’ve got to be thinking about all of these things from the get-go.

Ultimately, no one knows what Gateway 3 will fully entail, so if you’re not preparing for it, start now. Willmott Dixon is preparing for Gateway 3 by enhancing its pre-start procedures, working through key deliverables before construction even begins.

The team goes through what they are building, what they will be evidencing and how often and what good looks like. Whitty stated that having these early on-site conversations has been driving value in production and efficiency and that there is generally less conflict on site.

By working closely with supply chain partners, behaviours become apparent. Their willingness to collaborate, but also how they plan, prepare and deliver to make Gateway 3 more achievable.

Are construction projects ready for Gateway 3?

While the built environment’s focus has been on Gateway 2, it highlights one question: Are we ready for what comes next? Gateway 3 is currently the big unknown. The unknown can be scary, but especially for those unprepared.

“We’ll deal with it later” can no longer be an option, as evidence is crucial to demonstrating that what is built is what was designed for Gateway 2. That means thinking ahead now and applying all practices across all projects.

Because, at the end of the day, this is about whole building safety and protecting lives. And sticking to the agreed plan.

This article is based on Quelfire’s London Build 2025 panel discussion, titled Gateway 2: What We Know Now. Craig Wells, Sales Director at Quelfire, was joined by Graeme Whitty, National Product Director at Willmott Dixon and Nasar Ishfaq, Director, Architect and Principal Designer at R5 Consultants, to discuss Gateway 2 and what they have learned since its introduction. However, this article touches on why you should look beyond Gateway 2 to Gateway 3. It also explains how to prepare for it.

BSR gateway 2 approvals rise to 71%

The Building Safety Regulator (BSR) made 323 gateway 2 decisions in the 12 weeks to 1 May 2026, with 71% of applications approved, according to its latest building control update.

Of all decisions made during the period, 62% related to London projects.

Applications covering 17,046 residential units were determined during the 12-week period, including approvals for 12,299 housing units. BSR said 36,984 units remain in live cases.

The regulator also reported receiving new applications covering up to 17,626 residential units over the same period.

BSR’s Innovation Unit, which manages more complex higher-risk building applications, made 33 decisions in the 12 weeks to 1 May, approving 24 applications, equivalent to a 73% approval rate.

Fourteen of those approvals were for London projects. BSR said all 14 Innovation Unit decisions in London during the period were approved.

The regulator said all-time Innovation Unit approvals now total 33, with a median approval time of 22 weeks. The unit is currently handling 143 live applications representing 27,900 residential units.

Gateway 2 approvals continue to rise

BSR also published updated figures on remediation applications. The number of legacy remediation cases submitted in 2024 has fallen to 20, down from 42 at the start of 2026, with a further 12 applications expected to be determined by mid-May.

The regulator said remediation approval rates are nearing its 2026 target of 65%.

Under BSR’s batching process, where applications are grouped for external assessment, the median time from a case being issued to a supplier to a full assessment being returned was four weeks across new build, remediation and refurbishment categories.

The regulator said 254 new build cases, 408 remediation cases and 758 refurbishment cases have been issued through batching so far.

Median times from issue to supplier through to decision were nine weeks for new build cases, 10 weeks for remediation cases and 11 weeks for refurbishment cases.

BSR said the number of long-term legacy cases has been reduced to eight, which are being managed separately as complex cases.

Transitional cases have risen to 43 after BSR took over higher-risk building projects previously managed by Assent Building Control following the company’s closure in November 2025.

Charlie Pugsley, acting chief executive officer of BSR, said the regulator was continuing to process new build and remediation applications while maintaining building safety requirements.

BSR update shows 108 new build decisions over 12 weeks to 25 February

BSR Gateway 2 update and reporting changes

The Building Safety Regulator (BSR) has set out planned changes to how it reports progress on Gateway 2 applications, alongside updated volumes for decisions, invalidations and live cases in the 12-week rolling period to 25 February 2026.

The BSR said it has changed how it represents application progress by removing invalid applications from progress percentages, describing invalid applications as those lacking basic critical safety information and normally invalidated within around one week.

Percentages of withdrawn, rejections and approvals are now shown as a proportion of the total number of applications that passed validation.

Closed applications across all categories totalled 639 in the past 12 weeks, including 273 invalidations.

The number of live applications of all categories was reported as 1,212.

Across all Gateway 2 categories, 65% of closed applications were related to London cases, with 404 made in the capital over the past 12 weeks.

Remediation improvement plan due to be announced

A remediation improvement plan is set to be formally announced and introduced over the coming weeks.

The plan is intended to improve the efficiency, quality and timeliness of applications for remediation projects.

It will focus on strengthening BSR resource capacity, improving internal processes and supporting industry to submit higher quality applications.

The update reported 86 remediation decisions made since December 2025, including 41 in London, and 77 new cases received.

There were 279 live remediation cases being processed, representing 24,282 units.

The BSR said late 2025 and early 2026 remediation applications are averaging around 18 weeks, with complex older remediation cases taking longer for decisions.

It said it will publish specific remediation guidance in the coming weeks, alongside improved feedback and support for applicants.

New build decisions, legacy cases and Innovation Unit activity

Gateway 2 new build applications in the 12-week rolling period to 25 February recorded 108 decisions, with 82 new applications received.

New build applications representing 15,178 residential units were received, with decisions on 23,197 units issued, including 10,514 approvals.

There were 31,191 units in live cases.

Legacy cases reduced from 60 at the start of December to three normal applications, with a separate cohort of 18 applications with significant technical issues moved into a complex case category.

The BSR said approval rates of legacy cases continue to be 53%.

The BSR Innovation Unit (IU) made 27 decisions in the past 12 weeks, including 10 in London, and is currently managing 123 live new build applications representing 26,224 units, with 69 of those in the capital.

Eleven applications have been approved with a median approval time of 18 weeks.

For post-validation applications, 33% are approved and 33% rejected, with the remainder under active account management.

Charlie Pugsley, Acting Chief Executive Officer of the Building Safety Regulator, said: “We continue to see improvements to the numbers of decisions being made for new build applications, and the numbers of safe homes being made available for the future.

“We also continue to engage even more closely with applicants to help improve the quality of those applications and that continues to see tangible results that will make a real difference.

“However, we recognise that current determination times are falling short of our targets for remediation.

“Our Remediation improvement plan, which will be formally announced and rolled out operationally over the coming weeks, will represent a targeted package of focussed measures to reset the system.

“But speed can never come at the cost of safety, whether that be for new build or existing homes.

“Our goal continues to be to ensure that industry can construct safe buildings, and that residents can see the essential safety improvements they deserve without unnecessary delays.”

The update also described a batching pilot for bundling new build and remediation applications for accelerated assessment, stating that initial data indicates faster processing times than previous methods and that the model remains under evaluation.

Building Safety Regulator becomes standalone body in Gateway 2 reform milestone

Gateway 2 framework and transition to standalone status

The Building Safety Regulator officially became a standalone organisation on 27 January 2026, marking a structural shift in the delivery of Gateway 2 building control oversight.

The Building Safety Regulator (BSR), previously part of the Health and Safety Executive (HSE), transitioned to an arm’s-length public body under the Ministry of Housing, Communities and Local Government, paving the way for the creation of a single construction regulator as recommended by the Grenfell Tower Inquiry.

The regulator was established in 2021 following the Grenfell Tower tragedy, with full statutory powers introduced under the Building Safety Act 2022.

The move formalises a broader mandate that extends beyond high-rise buildings to include responsibility for safety standards across all buildings in England.

The transition follows what BSR described as an operational reset in its role as the building control authority for higher-risk buildings, supported by the introduction of its Innovation Unit and new efficiency measures.

These changes were positioned as part of efforts to improve operational delivery, target regulatory guidance and support competence development across the construction sector.

Regulatory mission, leadership and sector response

Lord Roe, Chair of BSR, said: “Today is a decisive and important step in strengthening building safety and a milestone that marks our evolution into a standalone regulator.

“While the creation of BSR in 2021 was a watershed moment, today is about looking forward to a single construction regulator that brings coherence to a once-fragmented system.

“We will know we are successful when residents acknowledge we have made the built environment safer.

“Today is about continuing to support homes being built safely while fulfilling our primary mission: ensuring we are all building better and living safer, together.”

Charlie Pugsley, Acting Chief Executive Officer of BSR, said: “Today is a significant new chapter for BSR, with a clear signal that while we must continue to focus on improving our operational delivery for both new build homes and occupied HRBs, our mandate extends far beyond high-rise oversight to a broader responsibility for safety and standards across buildings in England.

“By driving professional competence and refining regulatory guidance, we can ensure a holistic approach that spans from initial design through to lifelong building management.

“Our commitment to robust enforcement and cultural transformation serves a single, vital purpose in 2026 and beyond – restoring resident confidence and trust in the built environment.”

Samantha Dixon, Building Safety Minister, said: “Everyone deserves to live in a safe home and we are determined to deliver lasting change to make this a reality.

“The Building Safety Regulator sits at the heart of this mission, and today launching a new body is an important step in realising sector wide reform.

“I look forward to working with the new leadership team on our journey towards the Single Construction Regulator.”

Mark Reynolds, Executive Chair of Mace Group and Chair of the Construction Leadership Council, said: “Over the last twelve months we’ve seen a very tangible shift in how BSR has worked with the Construction Leadership Council and developers across the country, and the result has been a more effective process, enabling safer buildings to be commissioned and delivered faster.

“The UK needs confidence that the construction industry, the regulator and government are all working together to deliver new and safe housing at scale – and I believe this moment marks a major step forward on that journey.

“As an independent body and working under the leadership of Charlie and Andy I have no doubt we’ll see more positive progress during 2026.”

The transition formalises BSR’s independence and establishes its governance framework as the regulator works toward the development of a single construction regulator model.

Regulatory role and standalone status

The Health and Safety Executive (HSE) outlined the regulatory framework and operational changes following the transition to standalone status.

The HSE described the Building Safety Regulator as the national regulator responsible for improving the safety and standards of all buildings in England, established in 2021 following the Grenfell Tower tragedy, with full statutory powers introduced under the Building Safety Act 2022.

From 27 January 2026, BSR operates as a stand-alone executive non-departmental public body sponsored by MHCLG, with governance and accountability formalised while day-to-day regulatory activity continues.

The framework includes responsibility for regulating higher-risk residential buildings over 18 metres or seven storeys across design, construction and occupation through a three-stage gateway approval process.

BSR also acts as the building control authority for all higher-risk buildings, including hospitals and care homes, and oversees the performance of local authority and private sector building control bodies.

Charlie Pugsley, Acting Chief Executive Officer of the Building Safety Regulator, said: “This month marks a significant new chapter for BSR as a standalone body, with the knowledge that our new processes are driving improvements – evidenced by the fact we recently made the most decisions in our operating history.

“We are determined to build on this momentum by launching a Remediation Improvement Plan to tackle complex remediation cases and streamline resources.

“We will also be engaging even more closely with applicants to help improve the quality of new build HRB applications.

“By driving these improvements, we can ensure we keep essential construction projects being built, while upholding the critical safety standards that protect residents in both new and existing homes.”

Gateway 2 decisions and application volumes

The Building Safety Regulator published new building control approval data covering November 2025 to January 2026.

The Building Safety Regulator (BSR) recorded 698 Gateway 2 decisions across all application types in the 12 weeks to 24 January 2026.

Live applications across all categories totalled 1,159.

The final quarter of 2025 recorded 673 decisions by 31 December, compared with just over 200 in early 2025.

Across all Gateway 2 categories, 68% of decisions related to London cases, totalling 476 decisions in the capital since November.

In the 12 weeks to 24 January, 97 Gateway 2 new build applications received decisions and 99 new build applications were submitted.

New build applications represented 19,600 residential units.

Decisions were issued for 19,914 units, including 11,962 approvals.

Live cases represented 37,065 residential units.

Legacy, remediation and Innovation Unit performance

The update set out volumes and decision outcomes for legacy applications, remediation cases and the BSR Innovation Unit alongside new build activity.

Since November, 52 decisions were made on outstanding legacy cases inherited under the previous model, with 29 in London.

The approval rate for historic applications viable to receive a decision reached 87%.

The remaining 29 complex legacy cases were under assessment to determine whether continued resources were warranted or whether rejection and resubmission would be required.

Since 3 November 2025, 75 remediation decisions were issued and 73 new remediation cases were received.

Live remediation cases totalled 286, representing 24,949 units.

A batching pilot delivered 12 decisions, with a Remediation Improvement Plan scheduled to launch in the coming weeks to address application quality and streamline internal resources.

In the past 12 weeks, the BSR Innovation Unit (IU) recorded 39 decisions, with 27 in London.

The IU managed 111 live new build applications representing 25,226 units, including 61 in the capital.

Of cases progressing beyond validation, 30% were approved and 41% were rejected.

Initial validation failure rates reached 56%, linked to missing basic design information.

Industry reaction on Gateway 2 evidence and digital records

Rob Norton, UK Director at PlanRadar, said: “The BSR becoming a standalone body corporate is the final nail in the coffin for ‘analogue’ site management.

“For years, the industry has treated documentation as a post-script, something to be tidied up at the end of a project.

“Those days are over.

“An independent regulator, equipped with its own board and a dedicated enforcement mandate, isn’t going to accept a ring-binder full of blurred photos and missing signatures as proof of safety.

“The real challenge for Gateway 2 and 3 isn’t the regulations themselves, it’s the evidence.

“We are currently seeing a massive disconnect between on-site reality and regulatory reporting, which is the single biggest factor behind the Gateway delays currently stalling UK construction.

“If the BSR is to succeed in clearing these backlogs as an independent entity, it requires high-quality, tamper-proof digital data.

“Without a robust ‘Golden Thread,’ developers are essentially playing Russian Roulette with their completion certificates.

“This independence should be a wake-up call.

“The BSR now has the autonomy to set a higher bar for digital competence.

“We can’t expect to build the next generation of high-rise homes using the record-keeping standards of the 1990s.

“It’s time for the industry to stop viewing digital tools as an ‘extra’ and start seeing them as the only way to stay on the right side of an empowered regulator.”

Dr David Crosthwaite, chief economist at BCIS, said: “Data published by the Building Safety Regulator (BSR) in the past few months has spoken for itself.

“While more building control approval decisions are being made thanks to the new Innovation Unit, the speed of decision-making, specifically for remediation applications, must improve.

“Establishing the BSR as an independent organisation is certainly an important step toward unifying and simplifying how construction is regulated.

“It shows the industry is being listened to in the same way the BSR’s process adaptations did last year.

“That said, the BSR cannot afford to take its foot off the gas.

“Its new caseload is growing and construction’s residential market particularly would benefit from a slicker regulatory system sooner rather than later.

“Both private and public sector housing output has slowed and fewer approval holdups would go a long way to speed up project starts and the economic value they can deliver.”

Building Safety Regulator reports rising Gateway 2 approvals across high-rise projects

Record Gateway 2 decisions to 24 November

The Building Safety Regulator (BSR) has reported a record 272 Gateway 2 building control decisions to 24 November 2025 for new high-rise residential buildings, with overall determinations now totalling 578 since 31 August.

According to BSR, Gateway 2 determinations have continued to rise across all application types under its pilot operational processes.

The regulator reported an approval rate of 73%, with a large proportion of these decisions made through the recently enhanced approval with requirements route.

BSR stated that 76% of all Gateway 2 decisions to 24 November related to London cases, equating to 206 determinations in the latest update period.

Since 31 August, 409 Gateway 2 decisions have been made for London projects, with 85% of these utilising the approval with requirements pathway.

Historic applications, live cases and unit numbers

BSR confirmed that 40 of 103 historic new build applications submitted under the previous model had been resolved between 31 August and 24 November.

Of these 40 decisions, 20 related to London cases.

The regulator said a minimum of 9 further previous model applications have been assessed as ready to move through the approval with requirements route, subject to final checks and applicant agreement.

The remaining 54 historic applications are a key focus for BSR through to the end of the year.

Face-to-face meetings with regulatory partners are planned during December to finalise the majority of these outstanding cases.

Up to 24 November, BSR reported that new build applications representing 16,313 residential units had been received under Gateway 2.

Over the same period, approvals representing 11,138 units had been issued.

The regulator stated that 36,023 residential units are currently covered within 167 live Gateway 2 cases.

Innovation Unit and batching process in operation

BSR’s latest update highlighted the role of its Innovation Unit (IU) in managing high-rise residential applications.

The IU, described as a dedicated team of registered building inspectors and technical engineers, is currently handling 73 live new build applications representing 17,076 residential units.

According to BSR, the IU is delivering shorter processing times by validating applications rapidly and rejecting incomplete submissions so that applicants can address issues and resubmit.

The regulator reported that the early cohort of IU-managed applications is now being expedited to resolve technical issues, with first approvals from this route expected during December.

BSR is also implementing a batching process, launched in September, which groups applications for assessment by specialised engineering services suppliers.

Mixed-category bundles covering 217 new build and remediation cases have been dispatched under this pilot process.

The organisation said bundles continue to be issued weekly, based on supplier capacity.

BSR is developing a focused plan to apply lessons from these recent processes to remediation cases in the new year.

BSR outlook for Gateway 2 operations

BSR stated that its Operational Team is directly engaging with applicants and regulatory partners while working through individual blockers to keep cases moving.

The regulator linked this approach to the rate at which historic applications are now being closed.

Charlie Pugsley, Chief Executive Officer of the Building Safety Regulator, said: “The immediate, positive results we saw from our pilot operational changes have established a strong foundation for continued success.

“We are on track to continue to clear the majority historic cases by the end of December by engaging with applicants and our regulatory partners, seeing the benefits of our new batching system, and building upon the initial hard work of the Innovation Unit.

“Across BSR there is a confidence that projected milestones remain achievable, but rightly we remain cautiously optimistic.

“We are fully committed to supporting the pace of essential construction while upholding the essential safety standards that keep people safe in new and also existing homes.”

What the latest Gateway 2 data means for built environment projects

The latest Gateway 2 figures from BSR provide new detail on how high-rise residential building control applications are moving through the new regime.

Architects, fire engineering consultants and building services engineers working on high-rise residential projects can see that 73% of Gateway 2 determinations have resulted in approval, often through the approval with requirements route, which sets a clear pattern for how compliant submissions are being handled.

For developers, facility managers and risk assessors, BSR’s focus on resolving the remaining 54 historic applications, supported by face-to-face meetings with regulatory partners in December, indicates how historic cases may be brought into line with current expectations on structure and evidence.

The Innovation Unit’s management of 73 live applications representing 17,076 units, combined with rapid validation and rejection of incomplete submissions, sets practical expectations for the quality and completeness required at submission stage.

System installers and fire-protection contractors engaged in high-rise residential schemes can relate the reported unit and case volumes – including 36,023 units in 167 live cases – to likely sequencing of design, installation and inspection activity under the Gateway 2 process.

The batching of 217 new build and remediation cases for external engineering assessment shows how capacity is being organised around specialist review, which may affect how technical information is prepared and presented in complex projects.

UK Gateway 2 approvals stall as application rejections reach 75%

High rejection rates raise concerns over UK Gateway 2 application process

The Fire Protection Association (FPA) has reported that three-quarters of Gateway 2 submissions for higher-risk buildings are currently being rejected by the Building Safety Regulator (BSR).

The BSR, overseen by the Health and Safety Executive (HSE), said most applications are missing key fire and structural safety information, with issues stemming from misunderstanding requirements that have been in place for over a decade.

Tim Galloway, deputy director of the HSE, said: “Too many applicants don’t quite as yet understand what is expected of them.”

Galloway continued: “The missing details are fairly fundamental stuff. They relate to standards that are at least a decade and a half old in terms of what’s intended to be achieved, and that’s quite worrying that applications are not able to show fire safety and not able to show structural safety, which one would have expected.”

Galloway added: “What we have learned, I think, is that there’s more of a need for that investment in upfront design, that thinking to be done by those submitting the applications [happens] earlier, and that’s something that has required more transition for the industry than we’d expected.”

Industry guidance remains unclear as BSR reaffirms regulatory role

The FPA reported that many contractors have criticised the lack of clear guidance on how to meet Gateway 2 requirements.

Galloway said the BSR is cooperating with the Construction Leadership Council to support better guidance but noted the regulator’s role is not to author this material.

He stated: “I want industry to write that guidance, because it will be better than anything I could write.”

Galloway continued: “You need people who have got that deep construction industry experience, who understand the process, understand the right phraseology, understand how the designers and the architects and the other players interact, because they will write it with that in mind.”

Backlog of Gateway 2 approvals slows project timelines

According to data published by the FPA, the BSR has only approved 14 out of 45 Gateway 2 applications and one out of 13 Gateway 3 submissions that were transferred from private firms.

These figures reflect projects previously handled by private building control firms, including AIS Surveyors, which exited the market in 2024.

The HSE acknowledged the backlog and said: “We acknowledge there have been delays to processing approvals for building control applications and we are working to put this right.”

It added: “A backlog of complex in-flight higher risk projects which came into BSR after the collapse of private registered building control approver AIS Surveyors initially drove up processing times.”

BSR reports processing improvements but contractors push for changes

The HSE stated that increased resources have reduced Gateway 2 handling times for complex applications to 16 to 17 weeks, and category B projects to around 10 weeks.

The organisation said: “Outside of the backlog there are a small number of highly-complex ‘in build’ transitional cases which are not yet of a sufficient standard to be approved.”

It added: “We are taking a pragmatic approach to these cases to make sure building work can continue.”

The statement also noted: “We are confident that all the operational contingency measures we’ve put in place, including dedicated support from industry will also allow us to clear the applications in the backlog as we head into the new financial year.”

A construction source cited by the FPA argued that the current Gateway 2 system is causing construction delays and suggested deferring approvals to the final stages of build.

The source said: “The current system isn’t working but we all want to see safe buildings. We take pictures of everything for the Golden Thread so the proof will still be there for the end user and anyone who doesn’t comply with regulations will still be found out.”

UK Gateway 2 approvals stall as application rejections reach 75%: Summary

The Fire Protection Association (FPA) reported that the Building Safety Regulator (BSR) is rejecting 75% of Gateway 2 submissions for higher-risk buildings.

The BSR said most applications are missing essential safety information.

Tim Galloway of the HSE said the failures relate to long-standing design standards.

Galloway stated that better upfront design is needed.

Contractors have said clearer guidance is required to meet Gateway 2 requirements.

The BSR said it is working with the Construction Leadership Council on guidance but expects industry to lead it.

Only 14 out of 45 Gateway 2 applications and one out of 13 Gateway 3 applications transferred from private firms have been approved.

The HSE said the backlog was worsened by the collapse of AIS Surveyors.

It reported that processing times for new applications are now improving.

Complex cases still face delays due to application quality.

Some contractors want Gateway 2 approval moved to later project stages.